notice of completion


Also found in: Acronyms.

notice of completion

A notice typically given by contractors performing construction or improvement work for state or local governments;advising of the completion of the work and the necessity to file any liens within the required time period afterward.Many times the notice will run in the legal section of the local newspaper,although there may be a central location for filing them.

References in periodicals archive ?
Furthermore, as described below, these timeframes change once a Notice of Completion is filed.
Upon final completion of a project, an original contractor, owner, lender, surety or title company related to the project may file a Notice of Completion with the SCR.
However, these time limits only apply if the property owner provides notification to the claimant within 10 days after recording the Notice of Completion or Notice of Cessation.
Upon final completion of a project, an owner, lender or surety related to the project may file a Notice of Completion with the SCR.
When it goes into effect, it will replace what we have been doing with the filing of notices of commencement, and preliminary lien notices and will introduce the filing of a notice of completion.
Whether or not a Notice of Completion is filed will determine the time limitations.
An application for a lien and notice of lien must be filed within 45 days after the owner or general contractor completes publication of the notice of completion and files the same in the circuit court.
A notice of completion is a document filed and distributed by the owner that informs all entities that provided labor or materials that the project is complete.
Under the new provisions, every person with lien rights must record the notice and claim of lien within 120 days after "completion" of the building, structure or improvement unless a Notice of Completion is properly recorded and served.
7 716 m, based on the existing project documentation with the submission on behalf of the Employer notice of completion of works to the competent supervisory authority building and obtaining non-objection to use of constructed network infrastructure water supply in the village Meadow (in the case of the need to obtain permission to use the built network).
Post Construction Services to include final project close out, recording of the Notice of Completion, and other assistance as required.
7716m, on the basis of existing project documentation with the submission on behalf of the Employer notice of completion of works to the competent supervisory authority building and obtaining non-objection to use of constructed water supply network infrastructure in rural Meadow (in case of necessity to obtain permission to use the built network).
Full browser ?